Text preview for : 24644A(PIO-96CEInfo).pdf part of Keithley 24644A(PIO-96CEInfo) Keithley Misc 24644A(PIO-96CEInfo).pdf
Back to : 24644A(PIO-96CEInfo).pdf | Home
CE Mark Information
for the PIO-96
Keithley MetraByte certifies that this product has been tested and found
to be in compliance with the EMC directive and relevant harmonized
standards.
This document describes the limitation of certification, the declaration of
conformity, and the cabling instructions required for the CE Mark
configuration.
Limitation of Certification
This certification applies only to the operation of the product (with
specified cables and accessories) in the stated configuration and under the
stated operational and environmental specifications. Any modification,
misuse, or improper or inadequate maintenance of the product by the user
voids this certification.
Any deviation from the specific configuration may cause emissions or
susceptibility not within the allowed limits required by the stated
directive. It is the user's responsibility to demonstrate and maintain
compliance with the directive and standards.
Please read the next section, "Declaration of Conformity," for the specific
testing configuration for this product. Consult the Keithley Instruments
GMBH office (European importer) or Technical Support in Taunton, MA,
USA, for further information regarding the exact configuration details and
testing.
Part Number: 24644; Revision A 1
Declaration of Conformity
Application of Council Directive(s) 89/336/EEC
Standard(s) to which Conformity is EN50081-1, EN50082-1
Declared
Manufacturer's Name Keithley MetraByte
Importer's Name Keithley Instruments GMBH
Importer's Address Landsberger Str.65 D-82110 Germering, Munich
Type of Equipment Data Acquisition Plug-in Boards
Model Numbers PIO-96/CE with STA-50, CACC-2000, and JACKET shield
Year of Manufacture 1995
I, the undersigned, hereby declare that the equipment specified above conforms
to the above Directive(s) and Standard(s).
Place: Taunton, MA USA
___________________________________
(Signature)
Date: 01 January 1996 Mark Urban
(Name)
Quality Assurance Manager
(Position)
2 December 1995
Cabling Instructions for the CE Mark Configuration
The PIO-96/CE has four connectors, each of which can be connected to
an STA-50 through the CACC-2000 cable, as shown in Figure 1.
STA-50s
PIO-96/CE board
CACC-2000
cables
Figure 1. Connecting a PIO-96/CE Board to STA-50s
For CE Mark compliance, you must shield the CACC-2000 cables. The
procedure for connecting STA-50s to the PIO-96 and shielding the cables
is as follows:
1. Before installing the PIO-96/CE board in the computer, remove the
two clamp-adjusting screws and the clamp from the board's mounting
plate.
2. Feed a CACC-2000 cable through the hole in the mounting plate and
plug the cable connector into the I/O connector nearest the mounting
plate.
3. If you are using more than one cable, feed the next CACC-2000 cable
through the hole in the mounting plate, and plug the cable connector
into the next available I/O connector.
4. Repeat step 3 until all cables are in place on the board.
5. Wrap all of the cables together with the desired length of the flat
shield jacket, following the instructions in Figure 2.
Part Number: 24644; Revision A 3
(a.) Wrap all of the cables together so that
at least one-half inch of shield extends
through mounting plate, then use scissors
to trim the shielded jacket, as shown.
Flat Shield Jacket
PIO-96/CE
Trim away
1/2 inch
Fold Area
Flat Shield
Jacket
(b.) Fold shield back about one-half inch
through mounting plate to expose metallic
shield to clamping area, as shown.
PIO-96/CE
When re-installed, clamp
should make firm contact
with this collar, thereby
grounding the shield.
Figure 2. Installing and Clamping a Flat Shield Jacket
6. Re-install the clamp and clamp-adjusting screws so that the clamp
holds the cables firmly in place.
7. Connect the free end of each of the CACC-2000 cables to the
connectors on the appropriate STA-50s.
4 December 1995